We began
our Improve Phase by implementing a trial in two work pods targeting our goal
output of 58.
In this
trial we also kept a log of the issues that arose again preventing us hitting
our target. This is useful information and should always be tracked we found
from doing this trial and this project.
In this
trial we have tried to free up time for the operator and we have done this by
removing a step from the process
In the Analyse phase we realized that we prep
our part in polish very similarly to how grind finish their part so we moved
our belt and are trailing a new contact wheel with it in the grind job step.
This is to try and improve the finish quality of the part so when it arrives at
the polish job step there will be no need of the belt now moved to grind.
Also
the parts tend to receive damage at the blast operation just before the polish
job step so we brought in plastic guards for the grates in the blast cabinets and
rubber mats for the tables they use at that operation.
Also we Entered 3 weeks of data into mini tab in the trial
pods to generate a time series plot so we could better understand what was
going on, we used this to view the variation from when we began at a stable 54
with explainable outliers, to the variation seen in the trial weeks. We see it
start to get more under control near the end of the graph as the trial
progressed.
Some tools we found useful in this phase were logs for the operators to fill if something prevented them hitting their target, a time series plot and trials that had been decided in the previous phase.
![]() |